LEAN SIX SIGMA METHODOLOGY TO REDUCE EXCESS WASTAGE IN A BRICKYARD: A CASE STUDY

  • Juan Carlos Quiroz-Flores
  • , I. F. Varas
  • , Ahad Ali

Research output: Contribution to journalArticlepeer-review

4 Scopus citations

Abstract

Peruvian companies’ craft brick stands currently experience significant growth in sales. Thus brickyards seek to reduce the amount of waste to increase productivity and reduce cost overruns. In this study, the problem that has the greatest economic impact on a brick company is the excessive amount of waste. For this reason, the implementation of a model based on the Lean Six Sigma (LSS) methodology is proposed, applying Poka Yoke, Jidoka, Standardised Work, and Just in Time in order to reduce the number of defective bricks and cost overruns. The research project focused on the tambourine brick, the type whose percentage of generated waste is the highest in the production batch. To do this, the current situation was analysed; the main causes of the problem were identified and measured; and then Lean Six Sigma tools were used to attack the root cause. Finally, the proposed design reduced overheated bricks by 2.36%, wet bricks by 2.01%, and poorly stacked bricks by 1.8%, obtaining a 6.92% reduction in shrinkage and increasing the level of Six Sigma to 3.9, which contributed to the reduction of losses in the brickyard.

Original languageEnglish
Pages (from-to)92-105
Number of pages14
JournalSouth African Journal of Industrial Engineering
Volume34
Issue number2
DOIs
StatePublished - 2023

Keywords

  • brickyard
  • Jidoka
  • Lean Six Sigma
  • Poka Yoke
  • Standardized Work
  • waste

Fingerprint

Dive into the research topics of 'LEAN SIX SIGMA METHODOLOGY TO REDUCE EXCESS WASTAGE IN A BRICKYARD: A CASE STUDY'. Together they form a unique fingerprint.

Cite this