Abstract
At the beginning of 2020, the Coronavirus pandemic had various countries negatively affected in the development of their economic activities, as their industries had to interrupt production, hindering their performance and economic development. Before this occurrence, it was known that the evolution of construction labor performance on site was minimum and had high indicators of variability. Due to this, extensive literature reviews have presented Last Planner® System as a methodology to mitigate and improve performance, mostly, in building construction. However, this deficiency presents itself with more frequency in road projects and worsens because of the pandemic. Having this said, it is important to control labor performance during the sanitary crisis in road projects. Therefore, in this context, the objective of this investigation is to validate the use of Last Planner® System methodology indicators (Percentage of Plan Completed and Percentage of Constraint Removal) as mechanisms of labor control. The findings evidence a direct relationship between improving indicators of Last Planner® System and a better labor performance while meeting budgeted yields.This in turn has validated the use of Last Planner indicators. Regarding the Reasons for non Completion, the impact of external factors merits and additional investigation due to frequency of occurrence.
| Original language | English |
|---|---|
| Title of host publication | IGLC 2021 - 29th Annual Conference of the International Group for Lean Construction - Lean Construction in Crisis Times |
| Subtitle of host publication | Responding to the Post-Pandemic AEC Industry Challenges |
| Editors | Luis Fernando Alarcon, Vicente A. Gonzalez, Danny Murguia, Xavier Brioso |
| Publisher | Department of Engineering, Civil Engineering Division, Pontificia Universidad Catolica del Peru |
| Pages | 747-756 |
| Number of pages | 10 |
| ISBN (Electronic) | 9786124802546 |
| DOIs | |
| State | Published - 2021 |
| Event | 29th Annual Conference of the International Group for Lean Construction, IGLC 2021 - Lima, Peru Duration: 14 Jul 2021 → 17 Jul 2021 |
Publication series
| Name | IGLC 2021 - 29th Annual Conference of the International Group for Lean Construction - Lean Construction in Crisis Times: Responding to the Post-Pandemic AEC Industry Challenges |
|---|
Conference
| Conference | 29th Annual Conference of the International Group for Lean Construction, IGLC 2021 |
|---|---|
| Country/Territory | Peru |
| City | Lima |
| Period | 14/07/21 → 17/07/21 |
UN SDGs
This output contributes to the following UN Sustainable Development Goals (SDGs)
-
SDG 8 Decent Work and Economic Growth
Keywords
- labor
- Last Planner® System
- lean construction
- performance
- variability